How to make the 31 December battery install deadline

Quick answer

To get the 6.8 STC rate, your battery must be installed and certified by 31 December 2026. From 1 January 2027 the factor drops to 5.7, about 16% fewer STCs for the same battery. Book early: the date that counts is your electrical compliance certificate, not your contract.

Panda Power install in Gymea Bay NSW: 16.64 kWh GoodWe battery
Our install in Gymea Bay NSW

Why the date on the certificate matters

The Cheaper Home Batteries discount is set by the STC factor on the date the battery is installed, and a battery is treated as installed when the certificate of electrical compliance is issued. That certificate is issued when the install is finished and tested. See how the battery rebate works for the full rule and sources.

Steps to make the deadline

  1. Free proposal. Send us a recent power bill and tell us about your home.
  2. Site inspection. We check your switchboard, the battery location and your existing solar.
  3. Network approval. We apply to your electricity network for approval before connecting.
  4. Install and certificate. The battery is installed, tested and certified. That date sets your rate.

What can push an install into January?

Switchboard upgrades, network approval times, roof or access issues and the Christmas period can all add time. December install slots are limited, so the earlier you start, the more room there is to sort these out before 31 December.

Related project

A real Panda Power install that shows this topic in practice.

What it costs

Home batteries from $6,999 to about $15,999

base prices after rebates, inc GST, as at October 2026

What affects the price: battery size, brand and inverter, whether you already have solar, backup wiring, and any additional work at your home.

Base price for a standard install, after government rebates, inc GST, as at October 2026. Additional work such as switchboard upgrades, three-phase changes or complex installs is reviewed and quoted separately.

Get a fixed quote → · See battery prices →

FAQs

Does signing a contract in December lock in the 6.8 rate?
No. The rate is set by the date on the electrical compliance certificate, which is issued when the install is finished and tested.
What if my install slips into January?
It gets the January rate of 5.7 STCs per usable kWh instead of 6.8.
Do I apply for the rebate myself?
No. Your accredited installer applies the discount on your quote through STCs.

Related guides

More practical guides from the Panda Power team.

Panda Power install in Heathcote NSW: 27.99 kWh AlphaESS battery

Rebates · 4 min read · 3 November 2026

Will the battery rebate drop in 2027?

Yes. The federal battery discount falls from 6.8 to 5.7 STCs per kWh on 1 January 2027 and to 5.2 on 1 July 2027. Here is what that means for a typical battery.

Read article →
Panda Power install in Loftus NSW: 16.6 kWh GoodWe battery

Rebates · 3 min read · 3 November 2026

Battery Rebate for a 10 vs 20 vs 30 kWh Battery

How the federal battery discount changes with battery size, worked through for 10, 16, 20, 24 and 30 kWh at the 2026 rate and the 2027 rates.

Read article →

Related

Sources: DCCEEW, Cheaper Home Batteries Program; DCCEEW, Eligibility information; Clean Energy Regulator, Solar batteries; Clean Energy Regulator, Calculate STC entitlements. Last checked 5 November 2026.

56 days left

Install before 1 January 2027